Wiltshire Council is the highway authority for its streets, so it decides on a dropped kerb (a vehicle crossover, also called kerb lowering) and says who may build it. This is what its own pages say.
Towns and areas covered Amesbury, Bradford-on-Avon, Calne, Chippenham, Corsham, Devizes, Melksham, Royal Wootton Bassett, Salisbury, Trowbridge, Warminster, Westbury
- Fee to apply
- £310 non-refundable vehicle crossing licence fee for a standard application (application pack from 1 April 2026). It pays for the licence only, not the building work.
- Who builds it
- A contractor the council accredits. You nominate any contractor who has street works accreditation (SWQR for operatives) and at least £5 million public liability insurance; the council keeps no approved list and the licence must name a contractor.
- Typical total cost
- The council doesn't publish this
- Stated wait
- Turnaround for applications is up to 15 weeks unless there is a complication.
- Planning permission
- In some cases planning permission will be required; the council says it makes enquiries about planning on your behalf with its planning department as part of the application.
- Checked
- 11 October 2026 against Wiltshire's own page and its fees list
What else Wiltshire asks
Work must not start until written authorisation is issued. A further £82.50 is charged for any inspection more than 18 months after the licence is issued, and £40 to change the contractor on a licence.
How Wiltshire's fee compares
At £310, Wiltshire's fee to apply is £82 more than the £228 average of the 114 councils that publish one. It is the joint 89th lowest of the 114.
The councils in the South West that we've checked, lowest fee first:
| Council | Fee to apply | Who builds it |
|---|---|---|
| South Gloucestershire | £96.90 | Accredited contractor |
| Plymouth | £104 | Accredited contractor |
| Bournemouth, Christchurch and Poole | £130 | Council or contractor |
| Torbay | £192.40 | Accredited contractor |
| Swindon | £203 | Accredited contractor |
| Bath and North East Somerset | £205.26 | Accredited contractor |
| Gloucestershire | £310 | Accredited contractor |
| Wiltshire (this page) | £310 | Accredited contractor |
| North Somerset | £325 | Accredited contractor |
| Bristol | £357 | Accredited contractor |
| Somerset | £388.30 | Accredited contractor |
| Dorset | £390 | Council or contractor |
| Cornwall | £438 | Accredited contractor |
| Devon | £568 | Accredited contractor |
Apply to Wiltshire
Start on Wiltshire Council's dropped kerb page. Don't pay anyone to build it until the council has approved the application. Other councils' fees are in the table of every council.
No room to park off the street?
A dropped kerb needs space in front of the house for the car. If you park on the street instead, a charging cable can cross the pavement in a channel where the council allows it. Wiltshire: Coming Cross-pavement charging in Wiltshire, or which of the two fits your house.
Towns and areas in Wiltshire
Wiltshire Council looks after the streets of Amesbury, Bowerhill, Bradford-on-Avon, Calne, Chippenham, Corsham, Devizes, Durrington and Bulford, Ludgershall, Malmesbury, Marlborough, Melksham, Royal Wootton Bassett, Salisbury, Tidworth, Trowbridge, Warminster, Westbury, Wilton.
The towns are the ONS's built-up areas, placed on the council whose streets they are on. A village that isn't named is looked after by the council whose area it is in: type your postcode into the checker if you're not sure which.