The planning rules for no-driveway charging
Since 21 October 2026, a wall charger and a pavement cable channel don't need planning permission in England, within set limits. Your council's say over the pavement doesn't change.
The change is S.I. 2026/1056 (on legislation.gov.uk), made on 25 September 2026 and in force from 21 October 2026. Its full name is The Town and Country Planning (General Permitted Development) (England) (Amendment) (No. 2) Order 2026. It amends England's permitted development rules, so it applies in England only. The table follows the order's own wording.
A charger on your front wall
| Where | On a driveway, as before, or now anywhere else within the curtilage of a house or block of flats, such as a front wall on the pavement |
|---|---|
| What | A dedicated charging point, not "a standard domestic plug and socket" |
| Height | No more than 1.6 metres above the ground |
| Size | The unit and its casing no more than 0.2 cubic metres |
| How many | One per house or block of flats under the no-driveway route |
| On a wall by the pavement | Sticks out no more than 20 cm, and leaves at least 1.5 metres of footway between it and the edge of the road |
| Charging across a pavement | The cable must cross the footway "by means of an authorised cross-pavement solution" |
| Not covered | Conservation areas (for the no-driveway route), the curtilage of a listed building, scheduled monuments |
A rule that stopped wall chargers facing onto a road within 2 metres of it went in May 2025, under an earlier order (S.I. 2025/560). Some older guides still quote it.
The channel in the pavement
The order adds a new class of permitted development for "a pavement-embedded cable channel that allows a cable for the recharging of electric vehicles to safely cross a footway from a domestic premises to a parked vehicle". Mats and covers laid on top don't count. The channel must be installed "by, on behalf of, or with the authorisation of, a highway authority", which is your council, and taken out with the pavement put back when it's no longer needed. The same listed building, conservation area and scheduled monument limits apply.
What you still need
Before the change, a household could need three separate permissions: planning permission, the council's consent under section 178 of the Highways Act 1980 to put something across the highway, and a street works licence under section 50 of the New Roads and Street Works Act 1991. Only the first goes. The government said it "does not consider it appropriate to remove" the street works licence (the government response to the consultation (September 2026)). In practice your council's scheme bundles the consents into one application, and its answer is still the one that counts.
The charger itself must meet the wiring regulations (BS 7671), which an OZEV-authorised installer will see to. Work started under the old wording can carry on until 20 October 2027.
A three-pin lead
Not covered. The order excludes a standard plug and socket, and a cable laid across the pavement without consent is still a breach of the Highways Act. Section 162 makes a dangerous wire across a highway an offence.
Wales, Scotland and Northern Ireland
None of this applies there. Each has its own planning rules and its own approach to the pavement: Wales, Scotland, Northern Ireland.