Dropped kerbs in Hereford
Hereford is on the streets of Herefordshire Council, and that council decides on a dropped kerb (a vehicle crossover, also called kerb lowering). This is what Herefordshire's own pages say.
- Fee to apply
- £100 non-returnable fee to apply for a dropped kerb. If approved, a further £166 is payable before you start construction.
- Who builds it
- A contractor the council accredits. You appoint and pay your own contractor, who must hold £5 million third-party liability insurance and NRSWA qualifications.
- Typical total cost
- The council doesn't publish this
- Stated wait
- Up to 8 weeks for a decision; approval lasts three years; notification form returned at least 10 days before work starts
- Planning permission
- Needed for new or altered access onto A, B or C class roads; not normally needed on unclassified roads. May also apply to new dwellings, flats, listed buildings or industrial premises.
- Checked
- 11 October 2026 against Herefordshire's own page
What it costs in Hereford
Herefordshire charges £100 to apply, and a contractor the council accredits builds it. That is below the £228 average across the councils we've checked. Building the crossing is priced on top of the fee, once the council has looked at your pavement. Every council's fee is in the table of dropped kerb costs.
Apply to Herefordshire
Start on Herefordshire Council's dropped kerb page. Don't pay anyone to build it until the council has approved the application. Dropped kerbs in Herefordshire has the council's other rules and every town it covers.
No room to park off the street?
A dropped kerb needs space in front of the house for the car. If you park on the street instead, a charging cable can cross the pavement in a channel where the council allows it. Herefordshire: No scheme yet Cross-pavement charging in Herefordshire, or which of the two fits your house.